Production update – Completion

We are excited to announce that GODSPEED2 is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat has entered the Detailing and QA stage.

Until now, we have done almost main tasks to bring the boat to the final stage such as deck gear, all windows and hatches, companionway flooring, BBQ, galley bench top, aircon, steering, and all plumbing.

Currently, we’re working on antifouling works, trifold doors, bunk headliners, and companionway headliners. In addition, other detailing tasks and electric installations have been started.

Production Update – Fit out

Your boat has already entered the new stage after assembly – fitting out.

At this point, we have done almost main tasks related to rudders installation, companionway flooring, window liners, aircon unit installed, Lewmar deck hatches, and Laminex bulkheads.

Currently, we are working on cockpit drainage, plumbing 50% done, bunk headliners, deck gear 75%, and carpet works.

Production Update – Assembly

After both hull and deck were completed in our Lamination shed, the boat was transferred to SSY shipyard on 28th of March.

As you can see, the deck joining has been finished. Now, we are working on installing window liners and plumbing (thru-hulls).

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – lamination.

We are at the IGU stage for the hull while the deck is about to be demolded. Once completed, they will be delivered to Seawind shed for the assembly stage.