Production Update – Completion

We are excited to announce that ANTEDILUVIAN is now completed and moved to the storage yard, ready for launching.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

The boat is now largely outfitted, with most fittings installed, the electrical system nearing completion, and interior work almost finished. Our production team is focused on final touch-ups to ensure everything is completed as planned. With this progress, the boat will soon transition into the detailing and QC stage.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently completed the installation of the stanchions, windows and hatches, and engines.
Our production team is currently working on the following works: deck hardware (75%), electrical system (60%), plumbing and LPG (60%), steering system (50%), and timber fit-out (25%).

Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We recently completed the installation of the A-frame, forward beam, and engines.
Our Production team is currently working on stanchion (75%), windows & hatches (40%), deck hardware (40%), electric (35%), plumbing & LPG (35%), steering (20%), and gelcoat at 85%.