Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

We recently complete the hull-deck joining, engines & saildrive installation.

Our Production team is currently working on A-frame & beam (50%), electric work (15%), plumbing LPG at 15%, steering (20%), gelcoat (50%), stanchion at 25%, and deck hardware at 25%.

Production Update – Assembly

We are excited to inform you that your boat has been moved to the Assembly stage.

The hull and deck were successfully demolded a while ago. Our Production team is working on furniture module installation inside the hull, deck trimming & gelcoat repairs, getting well-prepared for hull-deck joining.