Your boat has reached 95% completion. Final touch-ups and detailing are being completed by our production team, after which the boat will undergo quality control inspection.















Your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the A-frame, stanchions, forward beam, as well as the installation of all windows and hatches.
Our Production team is currently working on trampoline, deck hardware (90%), electric work (80%), plumbing & LPG (80%), steering (70%), and timber fitout (65%).


















We are excited to inform you that your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchion, forward beam, windows and hatches.
Our Production team is currently working on trampolines, deck hardware (80%), electric work (50%), plumbing & LPG (70%), steering (50%), and timber fitout (30%).