Your boat is 95% completed, with all major systems tested & confirmed. There are some missing items on the way to arrive, and once they are fitted, the boat will be fully completed in great shape.















Your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the A-frame, stanchions, forward beam, as well as the installation of all windows and hatches.
Our Production team is currently working on trampoline, deck hardware (90%), electric work (80%), plumbing & LPG (80%), steering (70%), and timber fitout (65%).


















We are excited to inform you that your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchion, forward beam, windows and hatches.
Our Production team is currently working on trampolines, deck hardware (80%), electric work (50%), plumbing & LPG (70%), steering (50%), and timber fitout (30%).