Production update – Completion

We are excited to announce that Starlight is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this YouTube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat is progressing well in the Detailing & QA stage.

Until now, we’re in the final steps to get the boat completed and ready for launch. With the new update, we’re so excited to inform you that all the deck gear, interior flooring and forward bunk liners have been installed. Besides, there are some other main tasks that have already been done such as the steering, air conditioning, and plumbing.

At this point, we’re working on the electric work (75%) and the timber fitout has been started.

Production Update – Detailing & QA

The current status shows that your boat is being processed well in the Detailing & QA stage.

Since the last update, the boat has recently been installed with some critical parts to get closer to completion such as the companionway flooring, watermaker, galley bench tops, antifoul preparation, and Lewmar hatches.

Currently, we’re working on steering, plumbing (75%), deck gear (50%), and solar panel installation.

Production Update – Fit out

Your boat has already entered the new stage after assembly – Fitting out.

As you can see, the deck joining had been completed and the window- blacks had been painted. Currently, we’re working on thru-hulls (plumbing) and engine installation.

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our lamination stage.

At this point, hull infusion has started, and deck infusion is completed. After both the deck and hull are completed, they will be moved to another step for deck joining.