Production Update – Completion

We are excited to announce that Suzanne is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat is progressing well in the Detailing & QA stage.

Until now, we’re in the final steps to get the boat completed and ready for launch next month. We’re currently doing some final touch ups, fitting upholstery, and testing all the systems to ensure the boat will be fully completed before the Lunar New Year.

Production Update – Detailing & QA

Your boat is now at the driveway of the final stage.

Recently, we have completed all the tasks related to deck gear, windows, hatches, solar panels, antifouling, steering, helm windows, and BBQ. Then, the forward beam has also been installed.

We’re now working on electric works (50% done), plumbing (90%), and cabin headliners.

Production Update – Fit out

Your boat has already entered the new stage after assembly – fitting out.

At this point, we have installed the rudders and some other components have also been done such as window liners, Laminex bulkheads, companionway flooring, galley bench top, and carpet.

Currently, we’re working on deck gear (30% done), plumbing (75%), bunk headliners, salon windows, Lewmar hatches, and antifouling preparation.

Production Update – Assembly

Your boat has now entered the next stage after Lamination – Assembly.

The deck joining took place on October 22nd. At this stage, we plan to work on the rudders installation, flowcoat, blacks on the hardtop, steering tiller installation, deck hatch trimming, and thru-hulls trimming.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

At this stage, the hull is being done IGU and the deck moulding took place on 11th September. After both the deck and hull are completed, they will be moved to another step for deck joining.