Production update – Completion

We are excited to announce that Solitude II is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

The latest update indicates that your boat is making good progress in the Detailing & QA stage.

At this stage, the boat has been equipped with some critical parts to get closer to completion including all interior flooring, stove, trampoline, all solar, plumbing system, helm stations, and steering.

Our team is now focusing on completing the electrical work (75% done), timber fitout (75% done), trifold door, and finishing up the remaining detailing tasks.

Production Update – Fit out

Your boat is now in the fit-out stage where we have started to work on the key parts and the preparations before the boat goes to the QA & Detailing stage.

At this point, we’ve done some main jobs related to antifouling, forward beam, railing and lifelines, rudders installation, salon and forward opening windows, deck gear, helm seats, BBQ, galley bench tops.

We’re now working on composite deck hatches, steering, plumbing (75% done), electrical works (35%), and solar panel bracket.

Production Update – Assembly

Your boat has already entered the new stage after lamination – assembly.

Both the hull and deck had finished their journey in Lamination and the deck joining took place. Also, the stanchions are installed and the blacks are painted.

Currently, we’re working on plumbing stage 1 and thru-hulls. In the meantime, deck gear has just started (25% done).

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our lamination stage.

At this point, both the hull and the deck have demoulded. The team is just finishing up their work and getting everything ready for deck joining in the next stage – Assembly.