Production Update – Completion

We are excited to announce that Savoir Faire is now completed and will be wrapped up soon for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1600.

Production Update – Details & QA

We are excited to inform you that your boat has been moved to Details & QA stage.
We recently finished the dinghy davits, BBQ, cockpit roof, sliding door and sliding glass, galley bench tops, aircon, dagger boards, trampoline, engine room installations, and upholstery.
Our Production team is currently working on electric works (95%), timber fitout at 90%, flexiteek application. Plumbing and electric system testing are about to start.

Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently completed the deck gear, forward beam and trampoline, hardtop and solar panels.
Our Production team is currently working on plumbing 90%, electric works 50%, headliner, timber fitout at 50%.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed water maker installation, helm console and seats, dinghy davits, sliding door, all windows installed, washing machine in.
Our Production Team is currently working on sail drives installation, deck gear (50% done), plumbing 75%, electric works 30%, headliner, trampoline, and solar panels installation. Timber fitout also has just started.

Production Update – Fit out

Your boat has been progressing well in the first phase of fit-out stage.

We recently completed the jobs of pump, sanitary, thru-hulls, valves, tanks (100%), installing deck equipment (90%), jib track, daggerboard, Port head, and anchor.

Our Production Team is currently working on installing diesel hose, gas pipe, window in 80%, hardtop detailing (90%), helm seat, deck hatches, cross beam, and helm console.

Production Update – Fit out

It is exciting that your boat is now in Fit out stage.
We have completed the jobs of aft bunk bases, stanchions, pulpits, and lifelines.
Our Production Team is currently working on plumbing, window liners, tanks, port bathroom fitout, deck gear (30% done).

Production Update – Assembly

Your boat is taking final steps in the Assembly stage.
We have completed the carbon chainplates, galley base, window composite liners, black paint stb hull, splashboards at inner hulls, and some tanks installed.
Our Production Team is working on the black paint of port hulls, flowcoat works, making the interior floor insert, and continuing with deck gear.

Production Update – Assembly

It is exciting that your boat has made some progress in Assembly stage.

We have done hull and deck gelcoat repairs and engine room flow-coating. Our Production Team is now working on the window liners and interior bulkheads. The boat is gradually being well-processed to get to the next stage soon.

Production Update – Assembly

We are excited to inform you that your boat is now in Assembly stage.

The hull and deck was already joined. We have also done some jobs with bathroom gelcoat repairs, daggerboard casings installed and composite deck hatch trimming. Our production team is now working on hull and deck gelcoat repairs and engine room flow-coating.

Production Update – Lamination

Your SC705 is taking some significant progress to reach final steps in the lamination stage.

The hull and deck were demolded and Lamination Team is doing the grinding and trimming inside the boat. The team will check around the boat to ensure the best appearance before handing to SW1600 Team for assembly.