Production Update – Completion

We are excited to announce that Flying Tiger is now completed and will be wrapped up soon for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1600.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.
We recently completed the anchor/chain system, hardtop installed, all hatches, trampoline flange and fwd beam, mast base, aircon, plumbing.
Our Production Team is currently working on electric (90% completed), remaining engine room installations, solar panels, galley fitout, interior liners, general timber fit out (30% done).

Production Update – Fit out

Your boat has been progressing well in the second phase of Fit out stage.

We recently completed the deck gear, helm seats, fwd beam, hardtop, tanks, and all deck hatches installation.
Our production team is currently working on plumbing 90%, engine room insulation, electric jobs 75% completed, daggerboard installation, early timber fitout.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed the composite helm console, all windows and portholes, longeron, and timber fitout preparation
Our Production team is currently working on plumbing 50%, deck gear 20%. Engines arrived are also being planned for installation.

Production Update – Fit out

It is exciting that your boat now is taking the first steps in the Fit out stage.

We recently completed the pulpits, window liners, galley base, trampoline flange, Lewmar deck hatches, and aft bunks bases.
Our Production Team is currently working on plumbing (30%), Lewmar port hole windows.

Production Update – Assembly

Your boat has been progressing well in the second phase of assembly stage.

The jobs that we have recently done are window liners, tank bases, mast base, and stanchions.

Our Production Team is currently working on thru-hulls, galley base, daggerboards, salon ceiling liners, and transom gelcoat repairs.

Production Update – Assembly

Your boat has made some progress in Assembly stage.

Our Production Team is currently working on liferaft compartment, installing under-wingdeck sheave boxes, and stanchions. With this progress, the boat will reach the fitout stage soon.

Production Update – Assembly

It is exciting that your boat has been moved to Assembly stage.
We have done the jobs on detailing of the hull. Our Production Team is working on transom hull-deck join glassing, glassing the salon door frame, and nonskid repairs.