Production Update – Completion

We are excited to announce that SAVID is now completed and left our factory to the port for launching.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1600.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.
We recently have finished all plumbing, galley bench top, trampolines, helm stations, solar panels, and antifouling.
Our production team is currently working on electric work phase 2 (90% done), timber fitout (90%), aircon, companionway flooring, water maker installation, and detailing tasks.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently done the engine room fitout, trampolines, forward beam, all solar panels, remaining steering installation, and all deck gear.
Our Production team is currently working on plumbing (75% done), the first phase of electric work (75% done), timber fitout (50%), aircons, and antifouling preparation.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently have completed remaining windows, hardtop installation, dinghy davits, FWD beam, composite deck hatches, toe rails, lifelines. longeron, and dagger boards.
Our Production team is currently working on deck gear (90% completed), plumbing (25% done), electric work phase one (50% done), tank installation, solar panels, and steering system.

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We recently done windows installation, longeron, and daggerboards.
Our production team is currently working on deck gear (75% completed), plumbing (25% done), the first phase of electric works (30% done), and tank installation.

Production Update – Assembly

Your boat is taking the final steps in Assembly stage.

We have recently finished the engine room preparation, galley base, and flowcoat works.
Our Production team is currently working on deck gear preparation works, fitting dagger boards, and thru-hulls.

Production Update – Assembly

Your boat is progressing well in the second phase of Assembly stage.

We recently completed the stanchions, pulpits, and composite chainplates.
Our Production Team is currently working on windows liners, galley base, floor inserts, and composite bunk base.