Production Update – Fitout

Your boat is now in the Fit-out stage where we have started to work on the key parts and the preparations before the boat goes to the QA & Detailing stage.

Recently, some main components on the boat have been installed, including pulpit, stanchions forward beam, A-frame, companionway flooring, galley benchtop, oven & stove. At this point, our production team has also installed the washing machine, all windows and finished the jobs related to steering system.

We are now working on antifouling preparation, plumbing (75% done), electric system (50%), and the composite deck hatches.

Production Update – Assembly

An exciting journey has just started. Your boat is progressing well in our Assembly stage.

The deck joining took place on April 18th, and the engines have also been installed. In the meantime, the internal joining work is nearly complete.

We are currently working on trampoline joint gelcoat repairs, transom glassing, and gelcoat repairs.