Production Update – Assembly

Your boat has progressed to the next stage following lamination—Assembly.

The deck joining took place and some related tasks have been completed, including internal glass work, gelcoat repairs on the bow and transom, and painting of the side blacks. Besides, some other components have also been completed, including the rudder blades, forward beam, A-frame, trampolines, companionway flooring, and galley benchtop.

We are now working on steering system (50%), deck hardware (less than 25%), window liners (50%), carpet works (50%), and plumbing (50%).

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our Lamination stage.

Currently, we are working on the hull and deck gelcoat preparation. The targa bar has been installed, and the targa roof installation is in progress. Once both the deck and hull are completed, they will move on to the next step: deck joining.