Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat is making a significant progress in the new stage – Detailing & QA.

At this point, the stanchion installation has been completed. Progress continues steadily across other systems, with plumbing, deck hardware, and electrical each at 50% completion. Windows and hatches are nearing finalization at 90%, while the steering system has reached 70% completion.

Production Update – Fit out

Your boat has been moved to the new stage – Fit out.

Recently, we have completed some components on the boat including forward beam, A-frame, trampoline, and anchor box.

We are currently working on the steering system (50% complete), as well as plumbing, deck hardware, and liners (less than 25% complete).

Production Update – Assembly

An exciting journey has started. Your boat has been progressing well in Assembly stage.

At this point, the deck-joining has taken place, and the associated parts have been completed, including internal joining glassing, gelcoat repair, and trampoline flange.

We are currently working on transom sanding, gelcoat application, gelcoat repairs, and locker flowcoat.