Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat is progressing well in the Detailing and QA stage.

The boat has recently been equipped with some of the remaining detail parts, bringing it closer to completion. At this stage, the timber fit-out has been completed. The boat is now 95% complete, and we are currently planning for system testing.

Production Update – Fitout

Your boat is making a significant progress in the Fitout stage.

At this point, some key components have recently been completed, including stanchion, A-frame, forward beam, anchor box, trampoline, windows and hatches.

We are now working on the steering (50%), electrical and plumbing systems, LPG (75%), and timber fit-out (75%).

Production Update – Fit out

Your boat has been moved to the new stage – Fit out.

At this point, the A-frame, trampoline, and plumbing fittings have been completed. The anchor system and stanchions are both 75% complete. Work is also underway on the deck hardware, electrical systems, and steering, each currently at 25%. Overall, the fit-out is moving forward steadily with key components well in progress.

Production Update – Assembly

Your boat has already entered the new stage after lamination – Assembly.

Both the hull and deck have completed their journey in lamination, and the deck joining has taken place. We are currently working on inner side patching, window liner preparation, deck hardware preparation, and the station (75% complete).

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our lamination stage.

The hull and deck have already been demoulded, marking a significant milestone in the production process. This progress ensures that we remain on track for the subsequent stages of construction, moving steadily toward the final completion.