Your boat is progressing well in the final phase of Fit out stage.
We have recently done with the galley bench top, and salon ceiling panels.
Our Production team is working on remaining electric installation and timber fitout (90% done).












Your boat is progressing well in the Fit out stage.
We have recently done companionway flooring, plumbing, sliding door and windows. The daggerboards were installed and tested.
Our production team is working on remaining electric installation, timber fitout (75% done), galley bench top, salon ceiling panels. Flexiteek has arrived, ready to apply.
Your boat is progressing well in the Fit out stage.
We have recently done with the mast base, deck gear, trampoline, Lewmar hatches, davits, sliding door, fridge and freezer installed (waiting for bench top completion) and washing machine.
Our Production team is currently working on plumbing work (90% done), electric work (75%), timber fitout at 50%.
Your boat is progressing well in Assembly stage.
We recently completed installing stanchions, pulpits, chainplates, galley base, flowcoat works, composite window liners, forward bunk base, and trampoline flange.
Our production team is currently working on deck gear, aft bunk bases, floor inserts, and hull splashboard.