Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently done with the mast base, deck gear, trampoline, Lewmar hatches, davits, sliding door, fridge and freezer installed (waiting for bench top completion) and washing machine.

Our Production team is currently working on plumbing work (90% done), electric work (75%), timber fitout at 50%.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently done the dinghy davits, helm stations, all windows, and all deck hatches.
Our production team is currently working on plumbing work (75% done), electric work (50%), engine room fitout, and starting timber fitout.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently installed longeron, hardtop, helm seats, sliding door, remaining windows, rudder gudgeons, and deck gear.
Our Production Team is working on plumbing work (50% done), electric work (25%), and tank installation.

Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently have all windows installed (in curing stage) and completed bunk bases.
Our Production is currently working on deck gear (75% done), composite deck hatches, and plumbing works (20% done).

Production Update – Assembly

Your boat is progressing well in Assembly stage.

We recently completed installing stanchions, pulpits, chainplates, galley base, flowcoat works, composite window liners, forward bunk base, and trampoline flange.
Our production team is currently working on deck gear, aft bunk bases, floor inserts, and hull splashboard.