Production Update – Completion

We are excited to announce that Psipsina is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1160 Lite.

Production Update – Detailing & QA

Your boat has been progressing well in the Detailing & QA stage.

Until now, we have done some main tasks to get the boat closer to completion including rudders, gas piping, targa infill, all windows and hatches, all deck gear, lifelines, helm windows, trampoline, and mast base.

We’re currently working on steering, antifouling, plumbing (75% done), electric works (50% done), and shower glass installation.

Production Update – Fit out

Your boat has already entered the new stage after assembly – Fitting out.

At this point, the engine pods had been done and the black had also been painted.

Currently, we’re working on Laminex bulkheads, interior composite parts trampoline flange and anchor chain channel.

Production Update – Assembly

Your boat has entered a new progress – Assembly.

Both the hull and deck had finished their journey in Lamination and the deck joining took place on January 24th.

Currently, we’re finishing the internal glass works, bow and transom gelcoat repairs, and painting the blacks around hardtop windows.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Currently, we’re doing the IGU work on the hull and the deck is being laid up fibres. The demoulding process will occur after that to prepare for deck joining in the next stage.