Production Update – Detailing & QA

The team is now in the final stages of preparing the boat for its test sail.

As shown in the attached photos, most of the detailing has been finished, including the deck gear, forebeam, fridge, freezer, stove top, oven, and solar panel. The upholstery is also completed, and we are just waiting for the timberwork to be finalized.

Currently, the team is focusing on completing the timberwork, electrical installations, and trampoline setup.

Production Update – Detailing & QA

The current status shows that your boat is progressing well in the Detailing & QA stage.

At this point, targa and coachroof have been assembled and glassed. Gelcoat repairs of targa have been completed 80%.

The boat has recently been equipped with some critical parts to get closer to completion such as side hull windows, deck upper windows, front opening hatches, wiring and installation for the main power system ( Lithium batteries, DC/DC chargers, MPPTs, Charger/Inverter, Czone etc). Also, the bowspirit infrastructure has been completed and tested for bowspirit fitting. Frames for ceiling liner-upholstery installation have been manufactured and glassed.

Currently, the team is working on deck gear installations, all stanchions, deck fillers, windlass, exterior gelcoat works (70% done), fuel system plumbing, black water system plumbing, and preparation for timberworks. The upholstery kit production is due to start in week 20.

Production Update – Fit out

Your boat has been entering the Fitout 3 stage with a few more completed components.

Until now, the team has assembled the longeron and all interior window liners. Fresh water, seawater, grey water discharge pumps and bilge pumps have been installed. On the electrical part, the batteries, chargers, switch panel, and Czone installations have also been completed. The electrical assembly and wiring have just started.

The production team is currently working on the steering system, Targa bar, and trifold doors.

Production Update – Fit out

Your boat is progressing well in Fitout stage with some critical parts completed recently.

Based on the team’s updates, the deck-hull exterior joint has been completed and surface preparation is made for gelcoat. All interior laminations before window liners have been completed and backplates have been installed below deck.

At this stage, the team have done some tasks including exhaust system assembly, engine sea water filters, winches, laminated coachroof liner, rudder shaft, surface preparation of fixed window, exterior cockpit step lights and courtesy lights installation.

The production team is currently working on deck gear, stanchions, coachroof, steering system, and interior window liner.

Production Update – Assembly

Your boat has now entered the Assembly stage.

As you can see in the photos, the deck has already been placed on the boat and all geometrical adjustments are ready to be glassed on the hull.

Currently, the team is working on installing the steering system, exhaust system, and engine cooling system components.

Production Update – Lamination

Your boat has been progressing well in the lamination stage.

According to Turkiye production team, all furniture has been installed and glassed, the engines and saildrive tanks have also been installed at this point.

Currently, the team is working on liner installation and the starboard headliner is being glassed to get ready for the deck joining in the 3rd week of December.