Production Update – Detailing & QA

Your boat is making a significant progress in the Detailing & QA stage.

At this point, we have already completed several critical components, including the engines, targa seat, solar panels, windows & hatches, stanchions, lifelines, beam, and A-frame.

We are currently working on deck hardware (90%), steering (90%), plumbing & LPG (80%), electrical systems (60%), and timber fit-out (65%).

Production Update – Detailing & QA

Your boat is progressing well in the Detailing & QA stage.

The boat is 80% complete based on the previous configuration. As we have recently received some additional options, we are checking material availability and lead times and will keep you updated soon.