Your boat is progressing well in the Assembly stage.
At this point, some critical components have been completed, including targa bar, stanchion, lifeline, liners, forward beam, A-frame, trampoline, anchor box, and targa seat.
We are currently working on the windows and hatches (75% complete), deck hardware (50% complete), plumbing and LPG electrical systems, steering, and timber fit-out.