Production Update – Fit out

We are excited to inform you that your boat is progressing well in the Fit out stage.

Several key components have been successfully completed such as stainless steel parts, windows & hatches.
Our Production team is currently working on deck hardware (75%), electrical work (25%), plumbing (50%), steering (50%), and timber fitout (50%).

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

At this point, some critical components have been completed, including targa bar, stanchion, lifeline, liners, forward beam, A-frame, trampoline, anchor box, and targa seat.

We are currently working on the windows and hatches (75% complete), deck hardware (50% complete), plumbing and LPG electrical systems, steering, and timber fit-out.