Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1160XL.

Production Update – Detailing & QA

Your boat is progressing well in the Detailing & QA stage.

The production of your boat is progressing steadily, with several key stages moving forward as planned. At this point, your boat is 85% complete based on the current work order progress. All deck hatches have been fully installed.

We are now working on the electrical system (90% complete), timber fit-out (85% complete), steering system (90% complete), deck hardware, and windows.

Production Update – Detailing & QA

Your boat is making a significant progress in the new stage – Detailing & QA.

At this point, the stanchion installation has been completed. Progress continues steadily across other components including targa bar, lifeline, liners, forward beam, A-frame, trampoline, anchor box, targa seat, engines and deck hardware.

We are now working on electrical system (35%), plumbing (60%), steering system (60%), timber fitout (60%).

Production Update – Fit out

We are excited to inform you that your boat is progressing well in the Fit out stage.

Several key components have been successfully completed such as stainless steel parts, windows & hatches.
Our Production team is currently working on deck hardware (75%), electrical work (25%), plumbing (50%), steering (50%), and timber fitout (50%).

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

At this point, some critical components have been completed, including targa bar, stanchion, lifeline, liners, forward beam, A-frame, trampoline, anchor box, and targa seat.

We are currently working on the windows and hatches (75% complete), deck hardware (50% complete), plumbing and LPG electrical systems, steering, and timber fit-out.