Production Update – Detailing & QA

The production of your boat is progressing steadily, with several key stages moving forward as planned.

At this stage, we have installed some of the remaining components, including the solar panel system, flooring (in the saloon, corridors, and all cabins), and all headliners.

We are currently working on the electrical wiring and equipment, navigation system, finalizing the plumbing and steering systems, and completing the interior timber fit-out.

Production Update – Detailing & QA

Your boat is making a significant progress in the new stage – Detailing & QA.

The boat has recently been equipped with some of the remaining detail parts, bringing it closer to completion. These include stanchions, engines, windows and deck hatches, stainless steel cockpit seat parts, stainless steel dinghy davit parts, and BBQ.

We’re currently working on the deck hardware (85%), plumbing (45%), timber fitout (40%), steering system (35%), and electrical system (15%).

Production Update – Fitout

Your boat is progressing well in the Assembly 2.

We are currently working on the installation of the stanchions, black windows, deck hardware, steering, electrical system, and plumbing, all of which are making steady progress before moving on to the Fitout stage. We are also currently working on the bow and stern glassing and gelcoat repairs.

Production Update – Assembly

Your boat is progressing well in the Assembly stage where we have started to work on the key parts and the preparation for windows in the next stages.

At this point, the deck joining has taken place, and our team has also completed work on the longeron and gelcoat repairs. We have just started work on deck hardware, windows and hatches, steering, electrical, and plumbing systems.

Production Update – Assembly

Your boat has entered the Assembly stage.

Both the hull and deck have completed their journey in Lamination stage, and the deck joining has taken place. Currently, we’re working on the stanchion installation, deck hardware, steering system, electrical system, and plumbing.

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our Lamination stage.

Currently, we are working on the hull and deck gelcoat preparation. The targa bar has been installed, and the targa roof installation is in progress. Once both the deck and hull are completed, they will move on to the next step: deck joining.