Production update – Fitout

The current status shows that your boat is progressing well in Fitout 2 stage.

The boat has recently been equipped with some critical parts to get closer to Detailing & QA stage. At this point, we have completed the hull–deck interior laminations as well as the exterior and interior gelcoat repairs. The windows, fuel system, and bilge system have also been installed.

We are now working on the forebeam installation, and the fresh-water system installation will begin this week.

Production Update – Fitout

Your boat is progressing well through the Fitout stage, with several important milestones already achieved.

The hull-deck interior laminations and exterior gelcoat repairs have been completed. Interior gelcoat repairs are currently underway to ensure a smooth and high-quality finish throughout the interior areas. In addition, preparations for glass installation have started, with the installation itself scheduled for completion by the end of November as the team continues to make steady progress toward the next phase of construction.

Production Update – Fitout

Your boat is progressing well in the Fitout stage, and we have completed some critical components and preparations for the window installation.

As you can see in the photos, the hull-deck interior laminations were completed. We ‘re now working on the exterior and interior gelcoat repairs.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

At thAt this stage, the hull deck joining has been completed. All interior laminations of the deck, prior to the installation of window liners, have been completed. We are now working on some remaining lamination tasks before moving to the next stage.

Production Update – Assembly

Since the last update, your boat has already entered the new stage – Assembly.

At this stage, the ceiling liner installation in the starboard forward head, starboard aft cabin, and portside aft head has been completed. Center furniture, along with the laminations in the starboard aft cabin and portside aft head, have also been finalized. In addition, the hull has already been demoulded and the deck lamination is complete.

Besides, the installations of the engine and exhaust system, as well as the fit-out of the starboard aft cabin and portside aft head, are scheduled to begin shortly.

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our lamination stage.

As you can see in the photos, the hull has already been demoulded, and lamination of the center furniture, starboard aft cabin, and portside aft head has been completed. Ceiling liner lamination has now commenced, and deck lamination is currently ongoing.