Production Update – Assembly

Your boat is progressing well in the third phase of Assembly stage.

Deck joining was completed. Our Production team is currently working on helm seat inserts, remaining internal glass work, window liners, helm consoles. Various gelcoat repair work is also in progress and the first stage of plumbing work has started.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

Stanchions and pulpits were installed. Our Production team is working on deck gear (20% done), steering, headliners, aircon units installation, plumbing work (30%), and Laminex bulkheads.

Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently have forward beam, trampoline, windlass, and aircon units installed.
Our Production team is currently working on deck gear (50% done), steering, plumbing (50%), electric installations(30%), and forward opening windows.

Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently have trampoline installed, and all windows fully completed.
Our Production team is currently working on remaining engine room fitout, electric work (75% done), timber fitout (35%), remaining steering installation, and plumbing (75%).

Production Update – Fit out

Your boat is progressing well in the third phase of Fit out stage.

We recently completed some jobs like plumbing, helm seats, deck gear, salon flooring, and helm station installation.
Our Production team is currently working on electric installation (80% done), timber fitout (75%), TV compartment, antifouling, and BBQ installation.

Production Update – Details & QA

It is exciting that your boat has been moved to Details & QA stage.

We recently have done with solar panels, deck gear completed, helm station installation, galley fitout, all interior flooring, plumbing work, and liferaft installed.
Our Production team is currently working on electric works (90% done), timber fitout (75% done), flexiteek preparation, and detailing work.

Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently have all windows installed (in curing stage) and completed bunk bases.
Our Production is currently working on deck gear (75% done), composite deck hatches, and plumbing works (20% done).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently have completed remaining windows, hardtop installation, dinghy davits, FWD beam, composite deck hatches, toe rails, lifelines. longeron, and dagger boards.
Our Production team is currently working on deck gear (90% completed), plumbing (25% done), electric work phase one (50% done), tank installation, solar panels, and steering system.

Production Update – Fit out

You boat is progressing well in the final phase of Fit out stage.

We recently completed steering installation, galley top, Lewmar hatches, aircon, trampoline, and plumbing.
Our Production team is currently working on electric system (90%), antifouling, timber fitout (75%), nav station, and companionway steps