Production Update – Assembly

Your boat is progressing well in Assembly stage.

The deck was demolded, and currently targa bar and coach roof are installed on deck. The first phase of assembly is completed and the parts kit for Assembly 2 is in place and ready to be installed.

Production Update – Assembly

Your boat has been progressing well in the third phase of Assembly stage.

Hull and deck were joined. Our production team is currently working on installing composite helm stations, doing composite window liners, various ducting, interior composite parts, conduits.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

We recently completed antifoul preparation, hull gelcoat repair, trampoline flange, engines installed, rudders installed, liferaft box.
Our production team is currently working on plumbing (30% done), and interior gelcoat repairs.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed the antifoul preparation, rudders installed, stb side engine in.
Our production is currently working on plumbing works, installing all pumps, thru-hulls, steering works (30% done), companionway and bunk headliners, hull windows. Basic electric works have started. Gelcoat repairs are planned to be done in highly efficient way.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed hull windows installation, engine room fitout, cabin liner bases, water maker installed, composite helm stations, antifouling preparation.
Our production team is currently working on steering system (75% done), hull windows, plumbing 30%, deck gear, windlass, starting with hardtop windows. Port side gelcoat repair is also being processed, and next week starting with stb side. Gelcoat repairs are on track. Timber fitout is about to start for port side.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We recently completed steering system, all deck gear, salon flooring, trampoline, and forward beam
Our production team is currently working on electric system (75%), timber fitout 75%, galley fitout 50%, air-conditioning, shower glass, plumbing 75%, cabin side and headliners.


Production Update – Details & QA

We are excited to inform you that your boat has moved to Details & QA stage.

The boat is currently in the final stage. Final electric and fitout work is being done. Detailing works are being done, and BBQ area modified to fit new design. System and engine tests has started on 21st December.

Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video. 

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1600.

Production update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video. 

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Lamination

An exciting journey has started. Your boat has been progressing well in our Lamination stage.
At this point, Lamination Team is laying out the fiberglass and foams inside the hull mold. The hull is being made step by step and the deck will be started soon.