Production Update – Fit out

Your boat is progressing well in the Fit out stage.
We recently completed the anchor/chain system, hardtop installed, all hatches, trampoline flange and fwd beam, mast base, aircon, plumbing.
Our Production Team is currently working on electric (90% completed), remaining engine room installations, solar panels, galley fitout, interior liners, general timber fit out (30% done).

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination Team is step by step making the hull in its mold. The deck will also be laminated soon. The coach roof is also being made in its mold.

Production Update – Assembly

It is exciting that your boat has taken the first steps in Assembly stage.

The hull was demolded and Lamination Team is doing the Assembly 1 with furniture installed. The coach roof was also finished and ready for joining to the deck. The deck will be demolded soon, preparing for hull-deck join.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently completed the first plumbing and internal glass works. The hull and deck were just joined some days ago. Our team is working on engine installation right after that.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

The engines are installed and Laminex bulkheads are applied. The first plumbing stage is completed and QC checked, also the first stage of electric works have started.

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We recently completed installing pulpits and stanchions, all deck joint gelcoat repairs, and window liners.
Our production team is currently working on rudder installation, interior composite parts, cable trays, deck gear backing plates, helm seat inner liners, and plumbing (30% done).

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed many jobs including hull windows and rudders installed, antifoul preparation, and trampoline flange.
Our Production team is currently working on steering (75% done), aircon installation, electric works (50%), wall and head liners, plumbing (50%), deck gear (50%).

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We recently completed solar panels, trampoline, mast base, all windows, fwd beam, steering, plumbing, aircon.
Our production team is currently working on deck gear (75% done), electric works (75%), nav station, wall liners, galley fit out (50%).

Production Update – Details & QA

It is exciting that your boat now is in the Details & QA stage.

We recently completed: all interior flooring, timber fitout, galley benchtop and equipment.
Our Production team is working on: chart plotters installation, upholstery, testing plumbing and electric system, completing navigation console, doing detailing works.