Production Update – Details & QA

We are excited to inform you that your boat has been moved to Details & QA stage.
We recently finished the dinghy davits, BBQ, cockpit roof, sliding door and sliding glass, galley bench tops, aircon, dagger boards, trampoline, engine room installations, and upholstery.
Our Production team is currently working on electric works (95%), timber fitout at 90%, flexiteek application. Plumbing and electric system testing are about to start.

Production Update – Assembly

It is exciting that your boat is now in the Assembly stage.

The hull was handed over to assembly stage two weeks ago. The deck was finished and has been waiting for being joined to the hull. Our production team is currently installing targa bar, and preparing for hardtop installation.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The coach roof has been fully installed on deck.
Our production team is currently doing the dry fitting of deck, and doing trimming together with Lamination. Hull and deck joining will be started soon.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently finished the installation of engines and fwd opening windows. The plumbing-1 works and helm console with steering tiller were completed.
Our production team is currently working on steering, first stage electric works, pulpits, wall liners preparation, trampoline flange, head liners preparation, interior Laminex panelling.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

At this point, a few more detailed components have been finished including solar panels, helm seats, steering, galley bench tops, hydronic heating system, trampoline, companionway floorings, all hatches and windows.

Our production team is now working on deck gear (75% done), electric (25%), plumbing (75%), and bunk headliners.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.
All windows and steering system were completed, and solar panels applied as well.
Our production team is currently working on forward beam installation, deck gear (75% done), electric works (50%), bathroom gelcoat repairs, and plumbing (75%).