Production Update – Assembly

Your boat is progressing well in the third phase of Assembly.

We recently completed the center bathroom wall, side windows installed, window liners, coach roof on, helm consoles installed.
Our Production Team is currently working on the antifoul preparation, remaining hull gelcoat repair, trampoline flange. The basic plumbing works have started.

Production Update – Fit out

It is exciting that your boat now is taking the first steps in Fit out stage.

We recently completed installing diesel tanks, port side engine, and all window liners done.
Our Production Team is currently working on trampoline flange, helm console, center bathroom wall, basic plumbing, and electric preparation works.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed hull windows installation, engine room fitout, and cabin liner bases.
Our Production Team is currently working on checking all engine electronics, throttle system, preparing deck gear installation, and start of electric installations

Production Update – Detailing & QA

Your boat has been progressing well in the Detailing & QA stage.

We have recently done some other main tasks to get the boat closer to completion comprised of antifoul preparation, targa seat, all windows and hatches, all deck gear, all interior flooring, and galley benchtop.

Currently, we’re working on electric installations (75% done), the remaining plumbing (90% done), steering system, freezer, helm seats, and fuel tank installation.

Production Update – Detailing & QA

Your boat has been progressing well in the Detailing & QA stage.

Until now, we have done some main tasks to get the boat closer to completion including all steering, helm stations, all interior flooring, all plumbing, antifouling, and remaining solar panels.

Currently, we’re working on helm seats, electrical parts (75% done), and timber fitout.

Production Update – Fit out

Your boat has been progressing well in the fit out stage.
There are some jobs done on the boat like galley timber fitout, windlass, trampoline, interior flooring, all deck gear, composite deck hatches.
Our Production Team is currently working on: synthetic lifelines, electric works (75% done), cabin timber fitout (75%), plumbing (50%), setting up nav station.

Production Update – Fit out

Your boat has been progressed well in the Fit out stage.

We recently completed remaining hardtop windows and fwd opening windows, trampoline flange, hull gelcoat repairs, deck winches and jammers.
Our Production team is currently working on remaining deck gear, helm console fitout, composite deck hatches, starboarb side interior gelcoat repair, electric works (50%), timber fitout 20%, rudder installation.

Production update – Completion

We are excited to announce that Sweet Disposition is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this YouTube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1170.