Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Up to this point, the side hull and centre hull are already joined. The furniture of the forward cabins and the forward head has been assembled and glassed. Plus, our team has got the omegas glassed as well.

As you can see in the photo, all bulkheads have been manufactured and glassed in their correct locations. According to our team, we plan to place the fuel tanks in their locations and get this job completed within this week. Regarding the centre furniture, at this point, both port head and starboard aft cabin furniture have also been trimmed and we’re going to put them in their locations after some preparations.

Production update – Completion

We are excited to announce that Starlight is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this YouTube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Completion

We are excited to announce that Eora is now completed and left our factory to the port for sea trial.

Please see below for some photos of the boat before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination Team is step by step making the deck in its mold. The hull is being processed the IGU. We plan to demould them soon and Assembly will be started right after that.

Production Update – Assembly

Your boat has been progressing well in the first phase of assembly stage.

The hull and deck were joined and our production team is doing the final preparation inside the boat to get the boat ready for the second phase of assembly stage.

Production Update – Assembly

Your boat has been progressing well in the second phase of assembly stage.

The jobs that we have recently done are window liners, tank bases, mast base, and stanchions.

Our Production Team is currently working on thru-hulls, galley base, daggerboards, salon ceiling liners, and transom gelcoat repairs.

Production Update – Fit out

Your boat has been progressing well in the first phase of fit-out stage.

We recently completed the jobs of pump, sanitary, thru-hulls, valves, tanks (100%), installing deck equipment (90%), jib track, daggerboard, Port head, and anchor.

Our Production Team is currently working on installing diesel hose, gas pipe, window in 80%, hardtop detailing (90%), helm seat, deck hatches, cross beam, and helm console.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We have completed installing the aft cabin wall and ceiling and bow cabin port side. We also finished the plumbing works, main engine (100%), dinghy davits, escape hatches, daggerboard, anchor/windlass assembly, forward beam, hardtop, wall and headliners installation.

Our Team is currently working on air con (65% at saloon), electric winch, BBQ, gas, compass, installing steering system 50%, solar panels 90%, and deck gear installation (90%)

Production Update – Assembly

Your boat has made some progress in the second phase of assembly stage.

We recently finished the aircon ducting and composite furniture installation. Electric ducting and plumbing conduits were installed. The hull and deck will be planned to be joined soon.