It is exciting that your boat has been moved to the Assembly stage.
Our Lamination team is doing the assembly 1 jobs inside the hull. The deck is being completed, preparing for hull-deck join.






It is exciting that your boat has been moved to the Fit out stage.
We recently installed the forward opening windows, and the first plumbing stage was also completed.
Our Production team is working on electric works (20% done), plumbing (50%), wall and headliners, bulkheads and cabin walls Laminex application, and helm windows.
Your boat is progressing well in the Fit out stage.
Recent jobs that we have completed are all windows and hatches installed, fwd beam, and antifouling preparation.
Our Production team is currently working on plumbing (75% done), steering (75%), deck gear almost completed, timber fitout (30%), and synthetic lifelines.
Your boat is progressing well in the last phase of Fit out stage.
Recent jobs that we completed are solar panels, trampoline, mast base, all windows, fwd beam, steering, plumbing, aircon.
Our Production team is currently working on deck gear (75% done), electric works (75%), nav station, wall liners, galley fit out (50%).
It is exciting that your boat has been moved to Fit out stage.
We recently completed the cockpit winches, lifelines, and longeron installed.
Our Production team is currently working on windows installation, deck gear, fitting composite deck hatches, completing bunk bases, interior liners, first plumbing stage (25% done), fitting daggerboards.