Production Update – Fit out

Your boat is taking final steps in the Fit out stage.

We have completed all windows and hatches, BBQ, Aircon systems, deck gear, and trampolines
Our Production Team is working on the electric system (80% done), engine room installations, timber fitout (30%), wall and ceiling interior liners.

Production Update – Details & QA

Your boat is now in the Details & QA stage.

We have done the tasks of steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our Production Team is currently working on timber fitout (75% done), plumbing 80% and upholstery. Helm and nav desk electronics, remaining interior flooring, detailing works have been progressed well.

Production Update – Detailing & QA

Your boat has been progressing well in the Detailing & QA stage.

The boat is starting the final stage with the great effort put into timber kit installation.

Currently, we’re doing the final electrical installations and the detailing works are being done at the same time. The launch/ test sail might be put on hold until the skipper is available for the test sail ( around 28th August).

Production Update – Assembly

It is exciting that your boat has made some progress in Assembly stage.

We have done hull and deck gelcoat repairs and engine room flow-coating. Our Production Team is now working on the window liners and interior bulkheads. The boat is gradually being well-processed to get to the next stage soon.

Production Update – Fit out

Your boat has made significant progress in Fit out stage.

We have done with window glass and hatches installation, hull gelcoat repairs, steering column and steering equipment, cabin bunk frames, plumbing (75%), longeron.
Our production team is working on the preparation for wall and headliners installation, deck gear (50%), installing remaining tankage.

Production Update – Fit out

Your boat has made significant progress in Fit out stage.
Our Production Team are finishing step by step the electric works (75% done), the plumbing works (75% done). We are now focusing on the timber kit installation to get the boat well-timbered finished.

Production Update – Lamination

Your boat has made significant progress in Lamination stage.

The hull was demolded and our Lamination Team is working on trimming jobs around the hull. Composite furniture parts are being finished to get ready for being installed in the hull.

Production Update – Assembly

We are excited to inform you that your boat is now in Assembly stage.
All of the furniture parts were installed inside the hull. The deck is finished waiting to be joined with the hull. Its hardtop is being finished, then it will be joined with the deck soon. We have a hull-deck joining plan at the end of next week.