Your boat is taking final steps in the Assembly stage.
We have completed the carbon chainplates, galley base, window composite liners, black paint stb hull, splashboards at inner hulls, and some tanks installed.
Our Production Team is working on the black paint of port hulls, flowcoat works, making the interior floor insert, and continuing with deck gear.
Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have done with the installation of cockpit hardtop, helm consoles, and aft bunk bases.
Our Production Team is currently working on the deck gear (60%), inside fairing of daggerboard casing, interior wall liners, electric installations (30%), floor inserts, plumbing (75%), and salon headliners.
Production Update – Fit out
You boat is progressing well in the Fit out stage.
We have done the tasks of deck non-skid, mast base, deck hatches, solar panels, interior headliners preparation, and galley furniture. The companionway flooring, heating system, deck gear, composite deck hatches, trampoline and BBQ have also been completed.
Our production team is currently working on the steering system, the aircon, timber fitout (50%), electric system (50%), starboard aft bunk, and cabin healiners. Last late parts are estimated to arrive until last week of September and first week of October for installation.