Your boat has made some progress in Assembly stage.
The boat was moved over to 1370 main production line. Our production team is preparing the interior to get the hull be ready for joining in the next couples of weeks. The gelcoat surface on the bottom of the boat is also being finished.
It is great that your boat has taken final steps in Assembly stage.
The hull and deck were joined two weeks ago. We are currently working on window liners, starboard aft cabin modifications, hull and trampoline flange gelcoat repairs and installing pulpits. With this progress, the boat will be moved to Fit out stage in the next couples of weeks.
It is great that your SC605 is taking first steps in Fit out stage.
Pulpits were installed on the boat. We are currently working on window liners and modifications of starboard aft cabin. Gelcoat repairs of hull and trampoline flanged are in progress.
It is great that your boat has some significant progress in Fit out stage.
The window liners were installed. Antifoul surface preparation and chainplates had been completed. We are now continuously working on targa joint gelcoat repairs, fuel tank installation and plumbing.
Your boat has made some significant progress in Fit out stage.
The windows were fully installed on the boat at this stage. The electric works are ongoing with 50% done, plumbing 75% completed and deck gear 50% done.
Your boat has made some significant progress in Fit out stage.
Our production team have been done with the steering system, all windows including helm windows, deck gear, and Lewmar hatches. We are currently working on electric works (75%), plumbing (75% done), helm window, galley raw fitout, timber bulkheads, bunk raw fitout, solar panels and headliner.
It is so excited that your boat has reached the Detailing & QA stage.
We are currently working on cabins and saloon fitout with 50% done, electric and plumbing 75% completed. Navigation desk dashboard is about to be installed. Trifold door and deck nonskid repair have been done. Our 1370 team is waiting to have final timber fitout being provided to install. Upholstery was also completed.
At this point, we have done with other main tasks related to antifouling, trifold door, all windows and hatches, solar panels, deck gear, all flooring bunk liners, and steering.
We are working on timber fitout (50% done), helm station, and electric installations (50%).
Your boat has been progressing well in the Detailing & QA stage.
Until now, we have done almost main tasks to complete the boat including antifouling, Gori propeller and all windows installation. Furthermore, other detailing jobs have also been finished such as installing all interior flooring, laminex bulkheads, carpet, galley bench top, freezer, solar panels and trampoline. The steering system, Lewmar hatches and plumbing job were finally finished by our technical team as well.
At the moment, we have moved the boat to the next jobs and gradually go to the final steps as our production team is working on the trifold door, bunk headliner and deck gear ( approximately 75% done). Then, electric work is going to start shortly.
We had the hull & deck joined last week which is another mile stone for production.
In the next few weeks, there will be many changes happening on your boat. We will have engines in, steering mechanism installed, deck gear, etc. Along side with all that jobs we also have a plumbing team and electrical team working simultaneously to do all required plumbing, electrical, electronic systems includes: fresh water, black water, salt water and LPG.