Production Update – Fitout 1

This is the first Seawind 1190 Sport with Inboard engines. Jobs have been completed on the helm seats, all Lewmar hatches installation, carpet, fwd opening windows, anchor, trampoline, and bulkhead Laminex. We are currently working on steering, deck gear, helm windows, starting plumbing and electrics.

Congratulations – Jakdec is on her way!

Your Seawind 1160 Lite has been completed, and is on her way to Brisbane. The boat is scheduled to arrive at Brisbane on 17th November, 2020. A quick tour of the boat can be viewed via this Youtube video.

It has been a pleasure building this boat for you and on behalf of the entire team at Seawind Catamarans we wish you many years of fun filled enjoyment aboard your new Seawind 1160 Lite.

Fair winds and following seas,

Production Update – Assembly 2

Assembly stage is ongoing with its second phase.

Exterior: helm stations have been pre-fitted and coated with primer. Hull detailing has now been completed. Works are done with chain plates detailing, inboard bow section.

Interior: works have been completed for the installation of fwd fresh water pump, holding tank, and the moldings of escape hatches. Starboard head detailing, hot & cold plumbing, and window liners are 90% done. The preparation of window installation is half way ready. Other jobs including bed base and settee back have been started.

Engineering: water maker mounts, battery box, muffler mounts are all installed.

Production Update – Fitout 2

Many jobs have now been completed including the installation of trampolines, lifelines, Lewmar hatches, helm seats, galley benchtops with stove, plumbing, steering and Sado glass. Works are being carried out on deck gear, and electrical appliances. Boat is currently on schedule.