Your boat has made some significant progress in Fit out stage.
Our production team is working on electric cabling, forward opening windows installations, and trampoline flange. Deck gear and composite deck hatches are also being installed step by step.
It is great that your boat has some significant progress in Fit out stage.
All hardtop windows were installed, and the steering system was also done. Our team now is is preparing for furniture installation. They are also working on laminate bulkheads, electric works with fifty percent done, plumbing with around thirty percent in progress and doing remaining hull windows.
Your boat has some significant progress in Fit out stage.
All windows, deck gear and water maker were installed, and currently the team is preparing for timber kits installation.
Our team now is also working on electric installations with seventy five percent done, plumbing with fifty percent done and remaining deck gear which is almost completed. With this progress, the boat will reach the completion stage soon.
Until now, we have done almost main tasks to bring the boat to the final stage such as:Â antifoul preparation, rudder installation, bulkhead steerers, targa bench and BBQ, galley benchtop, Laminex bulkheads, trampolines, and all deck gear.
Currently, we are working on plumbing (75%) including watermaker, companionway floorings, and detailing works.
Until now, we have done almost main tasks to bring the boat to the final stage such as: anti-fouling, all windows and hatches installed, trampolines, helm station, all interior flooring, galley benchtops, and plumbing.
Currently, we are working on timber fit-out (75%), and electric installations (75%).
Besides, due to the global supply chain issue, there are a few parts coming later than our plan so we truly apologize that the estimated completion date has to be rescheduled to the first week of May. We will keep you posted if there are any changes to this new date.
Until now, we have done many main tasks to complete the boat including antifouling, all windows installation, deck hatches, deck gear, all interior flooring, plumbing, galley benchtops, stove & oven, forward bunk headliners, solar panels and cookout BBQ.
Currently, we are doing timber fit out, steering system, and electric installations (75%).
However, due to the global supply chain issue, we have quite a few missing parts that either pending for delivery date from the supplier or arrived later than we planned. We currently reschedule the completion date for your hull on the last week of April but we will keep you updated if there are any changes to this schedule.
Your SC705 is taking some significant progress to reach final steps in the lamination stage.
The hull and deck were demolded and Lamination Team is doing the grinding and trimming inside the boat. The team will check around the boat to ensure the best appearance before handing to SW1600 Team for assembly.
We are excited to inform you that your SC574 is now in Assembly stage.
Detailing jobs for transom steps and cockpit seat are finished. The bulkhead in port mid-ship was also installed. Our Assembly Team also trimmed the port side head, hatch lids, bulkhead inside fuel locker. Bunk cleat and bunk base were also on the boat.
At the moment, the team is installing the water unit for the cockpit tank, cutting the toilet cover and door wall.