You boat is progressing well in the last phase of Assembly stage.
We recently completed the windows liners, galley base, stanchions and pulpits. Our Production team is currently working on liferaft box, tanks installations, engine room flowcoat, and aft bunk bases
Your boat has been progressing well in the Fit out stage.
We recently completed the composite helm console, all windows and portholes, longeron, and timber fitout preparation Our Production team is currently working on plumbing 50%, deck gear 20%. Engines arrived are also being planned for installation.
Your boat is progressing well in the second phase of Fit out stage.
We recently completed the deck gear, forward beam and trampoline, hardtop and solar panels. Our Production team is currently working on plumbing 90%, electric works 50%, headliner, timber fitout at 50%.
Your boat is progressing well in the Lamination stage.
Assembly 1 for hull has been started on 18th December. The deck has also been started. Our Lamination team is laying out the fiberglass and foam inside the deck mold.
The deck was demolded, and currently targa bar and coach roof are installed on deck. The first phase of assembly is completed and the parts kit for Assembly 2 is in place and ready to be installed.
Your boat has been progressing well in the third phase of Assembly stage.
Hull and deck were joined. Our production team is currently working on installing composite helm stations, doing composite window liners, various ducting, interior composite parts, conduits.
Your boat is progressing well in the last phase of Assembly stage.
We recently completed antifoul preparation, hull gelcoat repair, trampoline flange, engines installed, rudders installed, liferaft box. Our production team is currently working on plumbing (30% done), and interior gelcoat repairs.
Your boat is progressing well in the Fit out stage.
We recently completed the antifoul preparation, rudders installed, stb side engine in. Our production is currently working on plumbing works, installing all pumps, thru-hulls, steering works (30% done), companionway and bunk headliners, hull windows. Basic electric works have started. Gelcoat repairs are planned to be done in highly efficient way.
Your boat has been progressing well in the Fit out stage.
We recently completed hull windows installation, engine room fitout, cabin liner bases, water maker installed, composite helm stations, antifouling preparation. Our production team is currently working on steering system (75% done), hull windows, plumbing 30%, deck gear, windlass, starting with hardtop windows. Port side gelcoat repair is also being processed, and next week starting with stb side. Gelcoat repairs are on track. Timber fitout is about to start for port side.
Your boat is progressing well in the last phase of Fit out stage.
We recently completed steering system, all deck gear, salon flooring, trampoline, and forward beam Our production team is currently working on electric system (75%), timber fitout 75%, galley fitout 50%, air-conditioning, shower glass, plumbing 75%, cabin side and headliners.