Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination Team is step by step making the deck in its mold. The hull is being processed the IGU. We plan to demould them soon and Assembly will be started right after that.

Production Update – Assembly

Your boat has been progressing well in the first phase of assembly stage.

The hull and deck were joined and our production team is doing the final preparation inside the boat to get the boat ready for the second phase of assembly stage.

Production Update – Assembly

Your boat has been progressing well in the second phase of assembly stage.

The jobs that we have recently done are window liners, tank bases, mast base, and stanchions.

Our Production Team is currently working on thru-hulls, galley base, daggerboards, salon ceiling liners, and transom gelcoat repairs.

Production Update – Fit out

Your boat has been progressing well in the first phase of fit-out stage.

We recently completed the jobs of pump, sanitary, thru-hulls, valves, tanks (100%), installing deck equipment (90%), jib track, daggerboard, Port head, and anchor.

Our Production Team is currently working on installing diesel hose, gas pipe, window in 80%, hardtop detailing (90%), helm seat, deck hatches, cross beam, and helm console.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We have completed installing the aft cabin wall and ceiling and bow cabin port side. We also finished the plumbing works, main engine (100%), dinghy davits, escape hatches, daggerboard, anchor/windlass assembly, forward beam, hardtop, wall and headliners installation.

Our Team is currently working on air con (65% at saloon), electric winch, BBQ, gas, compass, installing steering system 50%, solar panels 90%, and deck gear installation (90%)

Production Update – Assembly

Your boat has made some progress in the second phase of assembly stage.

We recently finished the aircon ducting and composite furniture installation. Electric ducting and plumbing conduits were installed. The hull and deck will be planned to be joined soon.

Production Update – Fit out

Your boat is progressing well in the fit-out stage.

We recently completed the cable trays and battery cables. The engines were installed, and so did the salon windows.

Our Production Team is currently working on forward opening windows, cabin liners, and deck gear with 30% done (winch installations). Plumbing has also been started at this stage.

Production Update – Fit out

Your boat is doing well in the second phase of fitting out.

We recently completed the electric cable trays and remaining windows tanks installations. 

Our Production Team is currently working on engine room cabling, plumbing works (30% done), hull gelcoat repairs, wall linter preparation works, and deck winches installation.