Production Update – Fitout

Your boat has been moved to the new stage – Fitting out.

After deck joining, our team has completed some other parts, including gelcoat repairs and the longeron installation. We are now progressing with the installation of windows and hatches, as well as the steering system.

Production Update – Fitout

Your boat is making a significant progress in the Fitout stage.

At this point, some key components have recently been completed, including stanchion, A-frame, forward beam, anchor box, trampoline, windows and hatches.

We are now working on the steering (50%), electrical and plumbing systems, LPG (75%), and timber fit-out (75%).

Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We recently completed hull-deck joining, hullside windows, and A-frame.
Our Production team is working on steering, deck hardware, electric, plumbing, and LPG (25%).

Production Update – Fit out

It is exciting that your boat has been progressing well in the Fit out stage.

We recently completed the installation of engines, forward beam, and A-frame.
Our Production team is currently working on gelcoat repair (85%), windows & hatches (60%), electric (25%), plumbing (40%), steering system (50%), and deck hardware (50%).

Production Update – Fit out

It is exciting that your boat has been progressing well in the Fit out stage.

We recently completed the installation of engines, saloon windows, hullside windows, A-frame, acnchor box, stanchion, deck hatches & hull sides hatches.
Our Production team is working on deck hardware (85%), plumbing, LPG, electric (75%), steering system at 80%, and trampoline.

Production Update – Lamination

Your boat is progressing well in the Lamination stage, with the hull lamination, furniture manufacturing, and installation of BHD, spider, and omega parts all completed. The forward starboard cabins have also been installed.

Work is currently ongoing on the center furniture installation and some preparation for deck joining.

Production Update – Completion

We are excited to announce that your boat is now completed and will be wrapped up soon, ready for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.