Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently completed the plumbing first stage and aircon units installed. Chainplates, Laminex bulkheads, windlass, forward beam and A-frame were also installed.
Our production team is currently working on rudder installation and steering, deck gear (winches), stage-1 electric works, windows and wall liners, and trampoline.

Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently have installed engines, windlass, fwd beam, helm windows, steering, solar panels, trampoline, fwd beam. Plumbing stage-1 was also completed,
Our production team is working on deck gear (50% done), electric installations (50%), hull windows, and plumbing (75%). Timber fitout has started.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed the forward beam, trampoline, aircon installation, all windows, helm seats, steering completed, and composite deck hatches installed.
Our production team is currently working on electric works (75% done), plumbing works (95%), deck gear (75%), Lewmar hatches, and timber fitout (50% done).

Production Update – Details & QA

It is exciting that your boat has been moved to Details & QA stage.

We currently completed the antifouling, steering, helm station electronics, engine controls, all plumbing, all deck gear, helm seats, timber fitout, and galley fitout.
Our production team is currently working on electric installations (95%), upholstery, trifold door, completing nav station.

Production Update – Fitout

Your boat has been progressing well in the Fit-out 2.

Since the last update,  we have recently finished some other components to get the boat closer to completion.

As you can see in the photos, the rudder shaft assembly has been completed and installed, the interior laminations of the deck have also been completed.

Production Update – Fit out

The current status shows that your boat is progressing well in Fitout 2 stage.

The boat has recently been equipped with some critical parts to get closer to Detailing & QA stage. At this point, targa and coachroof have been moulded and installed, longeron has been glassed to hull, moulding and joining of trifold doors have been completed ( not yet installed on the boat).

We’re now working on deck, cockpit and all interior joinery gelcoat repair works and the preparation for battery system.

Production Update – Fitout

Your boat has entered in the Fit-out 3. At this stage, we have done some critical parts and preparation for the windows in.

As you can see in the photos, side hulls glass frame gelcoat repair & finish tasks have been done. Our team has also completed their works on some other main components including bowsprit moulding/glassing work on longeron, moulding of all small parts like deck and floor hatches, moulding and joining of trifold doors.

Currently, we’re working on deck, cockpit, targa and all interior joinery gelcoat repair and plumbing system.

Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Completion

We are excited to announce that your boat is now completed and will be wrapped up soon to move to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Detailing & QA

SanJe is progressing well in the Detailing & QA stage.

At this point, your boat has basically been completed. After the lithium batteries arrive, it will be able to commission all the systems.

We genuinely apologize for any inconvenience this delay may cause and will keep you updated via the walk-thru video when the boat is completed.