We are excited to inform you that your boat has been moved to the Assembly stage.
Our production team is working on furniture installation inside the hull. Fitout tasks on the deck are also being carried out in the meantime.











Your boat is progressing well in the Assembly stage.
The hull and deck joining took place in early October. Pulpit and stanchions were installed. Our production team is currently working on transom gelcoat repairs, Laminex bulkheads, thru-hulls and other early plumbing tasks, and completing aircon ducting.
Your boat is progressing well in the last phase of Assembly stage.
We have recently done trampoline flange, hull windows, engines installed, Laminex bulkheads, and solar panels.
Our production team is currently working on deck gear (20% done), plumbing (35%), forward beam installation, salon windows, and mast base.
It is exciting that your boat has been moved to the Fit out stage.
We have recently done forward beam installation, trampoline, engines, hull windows, washing machine, aircon, and Laminex bulkheads.
Our production team is currently working on antifouling preparation, electric work (35% done), plumbing (75%), deck gear (75%), and rudder installation.
Your boat is progressing well in the Fit out stage.
We have recently completed forward beam and trampoline, rudder and steering, mast base, salon flooring, solar panels., all windows, composite deck hatches, and Lewmar hatches.
Our production team is currently working on electric work (80% done), timber fitout (50%).
Your boat is progressing well in the last phase of Fit out stage.
We have recently done all deck gear, antifouling, helm station electronics, interior flooring, and all plumbing.
Our production team is currently working on remaining electric work (90% done), galley fitout, headliners, and timber fitout (75% done).