An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
Our Lamination Team is step by step making the hull in its mold. The deck will also be laminated soon.


Your boat is now in the Details & QA stage.
We have done the tasks of steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our Production Team is currently working on timber fitout (75% done), plumbing 80% and upholstery. Helm and nav desk electronics, remaining interior flooring, detailing works have been progressed well.













Your boat has been progressing well in the Detailing & QA stage.
The boat is starting the final stage with the great effort put into timber kit installation.
Currently, we’re doing the final electrical installations and the detailing works are being done at the same time. The launch/ test sail might be put on hold until the skipper is available for the test sail ( around 28th August).