Construction is well underway at Lamination stage. Deck has recently been de-molded. Hull is in IGU and is scheduled to be de-molded on the third week of November, 2020.
Production Update – Fitout 2
Production Update – Lamination
Production Update – Lamination
Production Update – Fitout 1
The installation of all Lewmar hatches, trampoline, fwd opening windows, galley benchtops, bulkheads Laminex, and window liners is 100% completed. We are currently installing deck gear, hartop nonskid repair, bunk headliner surround, steering, electric (75% done), and just started with the plumbing work. Inboard engines will soon be installed.
Production Update – Assembly 2
Engines were able to be installed before deck joining. Trampoline and anchor roller assembly had been done. Currently working on window liners, Lewmar deck hatches, helm storage and ice box. The boat is on schedule.















Production Update – Fitout 2
Jobs have been completed on steering, deck gear, helm seats, Lewmar hatches, plumbing, helm windows, fwd opening windows, and benchtops. We are currently doing antifoul touch up, bunk headliners, and trifold door assembly. Electric works is about to be started.
















Production Update – Lamination
Hull is planned to bring over to our Seawind shed on 16th Oct after Lamination work is completed. Deck is ready and currently sitting in front of main office waiting to be moved to our Seawind shed for the joining to begin.