Your boat is progressing well in the Assembly stage.
The hull and deck were joined. Our Production team is doing glass work after deck joining and salon window cutouts.















We are excited to inform you that your boat is now in the Fit out stage.
We have recently completed all solar panels, windows, trampoline, and forward beam.
Our Production team is working on the first electric stage, deck gear (75% done), plumbing (20%), aircon unit installation, Laminex bulkheads, and composite deck hatch installation.
It is exciting that your boat is progressing well in the Fit out stage.
We have recently had engines installed, fwd opening windows installed, Laminex bulkheads, fwd beam and A-frame installed, Lewmar deck hatches, deck gear completed, all windows completed.
Our Production team is working on timber fitout (20% done), ceiling and wall liners, electric work (50%), and plumbing (30%).
Your boat is progressing well in the Fit out stage.
We have recently recently done the helm seats, interior flooring, solar panels, and all plumbing.
Our Production Team is working on steering, galley fitout, timber fitout (60% done), electric installation (90% done), wall and ceiling liners, and steering (75% done).
We are excited to announce that COCO is now completed and left our factory to the storage yard.
Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.