Your boat has marked the first steps in Assembly stage.
All of the furniture parts are being installed inside the hull. Our team is also done with the aircon ducting, windows liners and water tank installed.






We are excited to inform you that your boat is now in Assembly stage.
All of the furniture parts were installed inside the hull. The deck is finished waiting to be joined with the hull. Its hardtop is being finished, then it will be joined with the deck soon. We have a hull-deck joining plan at the end of next week.









It is exciting that your boat has taken first steps in Fit out stage.
We have done with the trampoline flanges, window liners, flowcoat works, and antifoul preparation.
Our Production Team is currently working on installing interior composite parts, saloon window frames, plumbing. Deck gear installation has also been started.











Your boat has made some progress in Fit out stage.
We have done with coach roof and targa bar gelcoat repairs, engine installation as well.
Our team is currently working on the electric cable trays, deck gear, interior gelcoat repairs, trampoline flanges, helm seats, forward opening windows, and plumbing works.











Your boat is taking the final steps in Fit out stage.
We have done with the steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our team is currently working on timber fitout, installing escape hatches, companionway steps, window and wall liners, trampolines, and upholstery. We will soon start with helm and nav desk electronics.














Your boat has entered the Detailing and QA stage.
Until now, we have done almost main tasks to bring the boat to the final stage such as deck gear, all windows and hatches, companionway flooring, BBQ, galley bench top, aircon, steering, and all plumbing.
Currently, we’re working on antifouling works, trifold doors, bunk headliners, and companionway headliners. In addition, other detailing tasks and electric installations have been started.













Your boat has been moved to the new stage after assembly – fitting out.
At this point, we have done some main tasks including Lewmar hatches, trampoline, forward opening windows, galley benchtop, window liners, companionway floorings, and carpet works.
Now, we’re working on deck gear (50% done), helm seats, windows installation, composite hatches, steering (75%), plumbing (75%), bunk headliners, and antifouling works.