Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We have recently installed engines, forward opening windows, Laminex bulkheads, forward beam and A-frame, and Lewmar deck hatches.
Our Production team is working on aircon installation, deck gear (50% done), plumbing (25%), and trampoline.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently installed all windows and hatches, aircon, deck gear, composite deck hatches, and antifouling preparation.
Our Production team is working on plumbing (50% done), electric (50%), and timber fitout (25%).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently done with helm seats, all deck gear, and solar panels installed.
Our Production team is working on steering, galley fitout, timber fitout (50% done), electric installation (75%), wall and ceiling liners.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We have recently completed solar panels, helm seats, helm windows, interior flooring, galley cabinets, and plumbing.
Our Production team is working on steering, wall and ceiling panels, helm displays, electric works (90% done), timber fitout (75%), and nav-desk console.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull and deck were joined. Engines, sail drives and rudders have been installed. Our Production team is working on window installation and deck hardware installation.