Production Update – Completion

We are excited to announce that Aradia is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Assembly

It is exciting that your boat has been moved to Assembly stage.
The hull and deck were demolded and Lamination team has stared working on installing the furniture inside hull. The team is also doing the fit out work for the deck and preparing for installing the coach roof on.

Production Update – Assembly

Your boat is progressing well in the third phase of Assembly stage.

Deck joining was completed. Our Production team is currently working on helm seat inserts, remaining internal glass work, window liners, helm consoles. Various gelcoat repair work is also in progress and the first stage of plumbing work has started.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

Stanchions and pulpits were installed. Our Production team is working on deck gear (20% done), steering, headliners, aircon units installation, plumbing work (30%), and Laminex bulkheads.

Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently have forward beam, trampoline, windlass, and aircon units installed.
Our Production team is currently working on deck gear (50% done), steering, plumbing (50%), electric installations(30%), and forward opening windows.

Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently have trampoline installed, and all windows fully completed.
Our Production team is currently working on remaining engine room fitout, electric work (75% done), timber fitout (35%), remaining steering installation, and plumbing (75%).

Production Update – Fit out

Your boat is progressing well in the third phase of Fit out stage.

We recently completed some jobs like plumbing, helm seats, deck gear, salon flooring, and helm station installation.
Our Production team is currently working on electric installation (80% done), timber fitout (75%), TV compartment, antifouling, and BBQ installation.