Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently completed the window liners, galley base installed, and tanks installed.
Our Production team is currently working on bow joint gelcoat repairs, deck gear bases, floor inserts, and bunk bases.

Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Fit out

Your boat is progressing well in the first phase of Fit out stage.
We recently completed the works of trampoline flange, catwalk, thru-hulls, escape hatches, engines in, and helm consoles.
Our Production team is currently working on deck gear (75%), hardtop installation, deck hatches, electric works (25%), plumbing 50%.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.
We recently completed the anchor/chain system, hardtop installed, all hatches, trampoline flange and fwd beam, mast base, aircon, plumbing.
Our Production Team is currently working on electric (90% completed), remaining engine room installations, solar panels, galley fitout, interior liners, general timber fit out (30% done).

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination Team is step by step making the hull in its mold. The deck will also be laminated soon. The coach roof is also being made in its mold.

Production Update – Assembly

It is exciting that your boat has taken the first steps in Assembly stage.

The hull was demolded and Lamination Team is doing the Assembly 1 with furniture installed. The coach roof was also finished and ready for joining to the deck. The deck will be demolded soon, preparing for hull-deck join.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently completed the first plumbing and internal glass works. The hull and deck were just joined some days ago. Our team is working on engine installation right after that.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

The engines are installed and Laminex bulkheads are applied. The first plumbing stage is completed and QC checked, also the first stage of electric works have started.