Production Update – Fitout 2

Fitout 2 stage is ongoing with new progress:

Exterior: hull and painting jobs are now 100% completed. Deck fit outs are 90% installed. All windows on deck are now in. Targa roof is scheduled to be installed very soon.

Interior: all the after cabins are being progressed smoothly – std and fwd cabins are 80% done. We will soon start on the port forward cabin. Starboard forward toilet has the plumbing system in place and the toilet is 20% completed.

Engineering: plumbing work is now completed. Daggerboard system is 90% finished. Works are being carried out on the steering system and anchoring system and have been done by 70%.

Upholstery job is started for the saloon, galley and std fwd bathroom.