Production Update – Assembly 1

This is our first SW1190 SPORT with Inboard engines. Deck was been moved over to SW shed and handed over at 29th August. Hull was moved over on 1st September, 2020. Targa bar and roof have been installed. Transom extension works are about to start. We plan to start the deck joining process around 10th September. Engines are planned to arrive at our factory this week.