Production Update – Assembly 2

Assembly stage is ongoing with its second phase.

Exterior: helm stations have been pre-fitted and coated with primer. Hull detailing has now been completed. Works are done with chain plates detailing, inboard bow section.

Interior: works have been completed for the installation of fwd fresh water pump, holding tank, and the moldings of escape hatches. Starboard head detailing, hot & cold plumbing, and window liners are 90% done. The preparation of window installation is half way ready. Other jobs including bed base and settee back have been started.

Engineering: water maker mounts, battery box, muffler mounts are all installed.