Production Update – Detailing & QA

Your boat has been progressing well in Detailing and QA stage.

Almost main tasks have been completed such as antifouling, all windows and hatches, deck gear, outboard engine, windlass, trampoline, companionway flooring, daggerboard housing and system.

The ongoing tasks these days include gasoline tank installation, and plumbing (75% done). Currently, electric installations have just started.