Your boat has been progressing well in the Detailing & QA stage, where several additional components have been completed to bring it closer to the final stages.
At this point, we have completed most of critical systems, including fuel system, bilge system, freshwater & sea water system, black water system, and ventilation system.
We are now working on Webasto, the LPG system (80%), all timberwork installation (60%), and electrical system (50%).