Your boat has been progressing well in the Detailing & QA stage.
We have installed the freezer, galley bench-top, all windows and hatches at this stage. Besides, the trampoline, all deck gear, helm window and synthetic lifelines have also been done.
We’re currently working on other parts consisting of companionway flooring, watermaker, plumbing (75% done), electric (50% done), and antifouling.