Your boat is progressing well in the Detailing & QA stage.
At this point, we have installed all windows, all Lewmar hatches, galley bench top, stove and trampoline. In addition, some other main jobs have also been completed including antifoul preparation, steering, companionway flooring, and plumbing.
We’re now working on the solar panel, air conditioning, deck gear (75 % done), and electrical system (30%).